Some useful history for younger folk!
Critical Path Analysis alongside Project Evaluation and Review Technique were developed in the 1950s as techniques to help model Projects, have a read about them if interested. My first degree was in Civil Engineering and at University I learnt these techniques the hard way, by hand calculation!Now software tools do all the hard work but in some you can break the golden rules of the technique so I like to keep things simple and in line with what I learnt was needed to produce a valid network:
- a Start and End milestone for the Project
- all tasks in between these two points have predecessor and successor tasks
Software tools often allow Work Breakdown Structures (WBS) to be documented in the schedule but encourage bad habits like dependencies linked to summary tasks.
(Read down later for definitions)
The Project - Making a Cup of Tea
What better example Project for an Englishman than to make a cup of tea. The Project work area is the worktop around a electric kettle in a kitchen. All non human Project resources are available in the kitchen and to start with let us make the Project Manager (David) do all the real work for a change :-)I have listed the Project tasks, durations, effort and task predecessors as follows. I don't mind you criticising my scheduling skills but please don't criticise my approach to make a good cup of tea except that I should really be using a teapot!
However when scheduling the Project I am going to use Minutes rather than Seconds for Duration and Effort to make the schedule more visible in most tools.
Other Project information is:
- Start date is 1 January 2015 at time 10:00
- There are no periods of non working to account for
- Remember to enter task duration & effort in minutes not seconds
- All tasks are carried out by one resource named David (to start with)
So please get scheduling and answer the questions below
Questions about Cup of Tea Project Schedule
Your questions are as follows:
- What task numbers are on the critical path for the basic network?
- If there is no consideration of over allocated resources, what is the earliest finish time of your Project?
- If you remove the overallocation of tasks to David, what is the earliest finish time of your Project?
- If you bring in as many team-mates as you like to help David, reallocating some of the tasks to these folk (but nobody is over-allocated work), what is the earliest finish time of your Project now and how many people did you require?
Definitions and other Help
Here are some definitions and general help for you:
- Task - a specific item of work
- Milestone - an event; it has no duration or effort. Typically used to denote a significant event such as the completion of a phase of the project or of a set of tasks
- Duration - the elapsed time to complete a task
- Effort - the amount of actual work required (in time units) for a particular task. A good illustration in the example "Cup of Tea" plan is the task "Boil Kettle". The effort required is minimal (basically to throw the switch) but the duration is governed by the amount of water, the temperature of the water poured into kettle and the capacity of the heating element
- Task Predecessor - A task that must be started or finished before another task or milestone can be performed
- Over-allocated Resource - a resource has been allocated more work in the plan than can be achieved in the available time
- Resource Levelling - process to remove the over-allocation (and ideally under-allocation) of resources and as far as possible avoid peaks and troughs in the resource schedule. Some tools allow this to be done at a click of a button but I have never had much success with this and prefer to do by hand guided by specific views setup. In a real-world project I will allow some over allocated resources (within reason) because estimates may not be correct and overtime can be used
- Work Breakdown Structure - decomposition of high level project deliverables into tasks and sub-tasks
- Critical Path - typically the path through the schedule of tasks which determines the shortest duration for the project. If any task on the critical path is delayed this will delay the completion of the project.
Answers
The answers for the questions posed above are:
- 1,14 (start and end milestones) and in terms of real tasks, 4, 6, 7, 8, 11, 12
- 14:30
- 14:50
- 14:30 with one extra person
6 Comments
Would love to use this in my class. Would you mind and if so how would you like me to reference it. Many Thanks
ReplyDeleteAnne, always pleased if someone finds the content useful! You might want to mention the site to the class in case there are other posts of value :-)
ReplyDeleteWork is constantly a standout amongst the most costly parts of any undertaking and it is something that each task administrator is observing nearly. At the point when the site foreman can see the improvement his group is setting aside a few minutes contrasted with anticipated advancement, he can conform his work loads and either get back on track or stay in front of calendar. online project management web app
ReplyDeleteAll at ease due to electric kettle.
ReplyDeleteContinuously i used to read smaller posts that as well clear their motive, and that is also happening with this article!
ReplyDeletefriv300online by For18xxx
LOL where's the teapot. Can't be English without a teapot :)
ReplyDelete