The difficulties of being a Project Manager
As a Project Manager you typically need to achieve things through team(s) and individuals that you have no line management responsibility for. This is often call matrix management, I sometimes call it managing people with one hand tied behind your back :-) Despite this you still need to get the Project delivered dealing with any Issues along the way. This may need you to land some punches!
1) Establish a Project Board to own the project or at a minimum a Sponsor who owns delivering the benefits of the Project. Once you have this in place you can use the Board as a whole or individual members of the board on an informal or formal basis to deliver a punch. Some examples of punches might be:
3) There may be others possibilities in individual circumstances so put your thinking cap on, "how can I land a punch on this person or team?"
What punches can I land?
Like a fighter you need to understand "what punches can I land and where should I land them for differing impacts, sometimes to soften up, sometimes to put on the canvas?". So what are the possible punches?1) Establish a Project Board to own the project or at a minimum a Sponsor who owns delivering the benefits of the Project. Once you have this in place you can use the Board as a whole or individual members of the board on an informal or formal basis to deliver a punch. Some examples of punches might be:
- an informal chat with a Senior User because there is an issue with some business resources. The message might be "We have a problem with Fred who is not delivering to the agreed plan and is making lots of excuses. Can you please have a quiet word with him and get him on track else I am going to have to formally raise this at the next Board meeting?"
- similar informal chats with other Board members for different resources
- using the regular Project status reports to highlight an increased probability Risk or maybe an Issue depending on the strength of the punch required
- changing the RAG status of the regular Project status reports to Amber (or Red) citing the reason for this being <the punch you wish to land>
- formally escalating a Project issue to the Board requesting assistance from them for resolution - the nuclear option, not your first one
3) There may be others possibilities in individual circumstances so put your thinking cap on, "how can I land a punch on this person or team?"
But telegraph your punch first
OK, so you have identified your range of punches. But don't overuse and try your hardest not to use because they don't aid team spirit.
Firstly, I will give the team / individual every opportunity to fix the problem I have raised through a discussion or two on a one to one basis. Secondly I will telegraph the punch by saying something like "if you don't achieve x by y" or "if I don't see a change in attitude by z" then I will need to <describe appropriate punch>. In this way you have given sufficient warning and this will minimise negative relationship impacts of landing the punch. But there will be some impact as nobody likes being hit!
Hopefully the threat of the punch achieves the desired result but sometimes it doesn't. If it doesn't then make sure you follow through with the punch that you said you would throw else your credibility will be lost (you have cried wolf).
Hopefully the threat of the punch achieves the desired result but sometimes it doesn't. If it doesn't then make sure you follow through with the punch that you said you would throw else your credibility will be lost (you have cried wolf).